Sheffield University

St George's Phase 2

St George’s Phase 2 has been one of Newell’s most challenging projects, carried out on the 9th and 10th floor of an occupied building.

This is, in no uncertain terms, a logistical nightmare!!! The 26 week program, with a circa value of 2.9 million, to deliver a state of the art Lab Facility. The project is now approaching its final 4 weeks prior to completion and handover.

Under the joint supervision of Rob Newell and Rick Hall the project has been run with military precision. The two floors are so heavily serviced, it was imperative that coordination of our subcontractors was paramount.

Below you will see a collection of photographs demonstrating this:

IMG_0884

Nearing Completion Lab Furniture Installed and protected.

IMG_0878

Installation of Electrical Control Panel

IMG_0874

Full extent of Lab Gas Installation

IMG_0871

Electrical Cable Tray receiving Cabling and Data

IMG_0869

Open ceiling with Heating and Flue Gases installed

IMG_0867

New Suspended Ceiling Grid in place, above is heavily serviced ceiling void

IMG_0864

Lab Gases Pipework and Extract duct in place for installation of Fume Cupboards. With Electrical Tray and Heating Pipes to complete the picture

IMG_0863

Fume Cupboards in place

IMG_0862

Heating and Cooling Air Handling Unit fitted at high level